High River AB: A partial closure of 2 Avenue NE is scheduled for Tuesday, September 2, to allow for road, curb and gutter, and sidewalk repairs. The closure includes 2 Avenue NE between 5 Street and Sunshine Trail / Hamptons Boulevard, with access maintained for Homestead Acres. The closure is anticipated to be in effect for the month of September.
In October, 5 Street NE will also be repaired and will be done in two sections. Work is anticipated to start at Sunset Way and go north to Little Bow Canal during the first half of October. The second section, running from Sunset Way south to 2 Avenue is anticipated to take place in the last half of October.
All construction work is pending weather and any unforeseen delays. Detour routes will be signed.
Pedestrians and drivers are reminded to watch for trucks and workers and to obey all safety signs and closures throughout town. Please be aware that barricades will be in place for public safety and will be left in place for lane closures even though construction crews may not be present.