Foothills School Division: Update on Capital Projects


 

Modular Classrooms

With the anticipated cost below the provincial bid threshold of $250,000, the Division is awaiting final approval from the Province to seek three bids rather than having to go through a lengthier tender process for this work. The scope includes moving and connecting the modulars as well as some remedial work to adapt these units, which were previously used by Notre Dame Collegiate students at École Senator Riley Middle School following the June 2013 flood. The five modulars are destined for C. Ian McLaren, Heritage Heights, École Percy Pegler and Spitzee Elementary schools, with the goal of having the units in place for September 2015.

New Division Office Building

The contract for the FSD Division Office-Alberta Government shared facility in High River has been awarded to Graham Group Ltd. and Gibbs Gage Architects. We are still anticipating a completion date of December 2016.